Locker Room Update 3/21/23

We are almost there!

With only a few steps left before we can open the temporary showers and rest rooms. Staff wanted to provide you a quick update on the progress that has been made.

  • The shower trailers have arrived and been placed.
  • The plumbing has been installed and will be connected on Friday and Monday.
  • The electrical connections have been installed and completed.
  • Water hookup and been installed and completed,
  • Tent covering and flooring is being installed as we speak.

We wanted to thank you for the your patience as we work to bring back these essential functions to you. We anticipate the facilities to open later next week. We will all breath a little sigh of relief once we are able to shower and have sufficient rest room space once again. Stay tuned for more updates very soon!