FWCC Locker Room Update: Tiling Continues

FWCC Locker Room Renovation Update! 🚧 (7/14/25)
 
Tiling is on a roll at FWCC! The men’s side is nearly finished, and you can really start to see the design coming together with the tile patterns taking shape. The sauna now has brand-new lighting, and crews will continue tiling for a few more weeks before moving on to locker installation. We’re excited to see it all coming together!

FWCC Locker Room Update: Tiling has Begun!

FWCC Locker Room Renovation Update! 🚧 (6/27/25)


We’ve officially wrapped up waterproofing and have moved on to tiling! The steam room tiling is nearly complete, giving you a first glimpse of the style you’ll be seeing throughout the new locker rooms as we move forward!

We’ve also started construction on the Sauna’s new wood benches and paneling, and things are really starting to take shape.

More updates coming soon!

FWCC Locker Room Update: Wall Installs & New Pool Deck Shower

FWCC Locker Room Renovation Update! 🚧 (5/29/25)
 
We’re making great strides! All drywall, cement board, and waterproof coatings have been successfully installed in the new locker rooms. Next up: painting and a significant amount of tile installation, there’s a lot of tile to go in!
 
As part of this phase, we also made upgrades to the leisure pool deck shower area, including new tile and the addition of a second shower for improved accessibility and convenience.
 
More updates coming soon stay tuned!

FWCC Locker Room Renovation Update: Concrete Slabs + Foundation Pours

FWCC Locker Room Renovation Update! 🚧 (3/19/25)
Another big milestone! Our crews have been hard at work on the slab and foundation concrete pours, setting the stage for the next phases of the renovation. With this solid foundation in the works, upcoming work will focus on pouring the remaining main walkway concrete, sloping drains, rebuilding ceilings and HVAC duct cleaning. Stay tuned for more updates as we keep moving forward!

FWCC Locker Room Renovation Update: Concrete & Construction in Motion!

FWCC Locker Room Renovation Update! 🚧 (3/3/2025)

Progress is underway! Our crews started pouring concrete for the curbing of wall structures and waterproofing layers between slab and foundation pours. Once this initial layer is complete, the next step will be rebuilding of walls and pouring of the concrete slab. Stay tuned for more updates as we move forward!