When the Slide and Play Structure replacement project started the original scope of work was to replace the large slide and the APU (Aquatic Play Unit) and to re-plaster the pool. At the time of the plaster removal at the end of November some serious problems and unseen issues such as, rust and corrosion in wall structures and water intrusion were uncovered that had to be addressed.
We went to the City Council on December 6th, 2022 with a change order of $112,700 to remediate serious and extensive rust to the rebar of the substructure of the entire leisure pool. This remediation included rust removal, treatment, extensive waterproofing, tile removal and replacement. In addition, zinc anodes were installed to prevent future rust. During this time like everything else supply chain issues arose that caused delays in obtaining product. Here are a few pictures of the current progress and installation of the Aquatic play unit.
We were hopeful and optimistic for a December 16th reopening and announced that date, but the issues above made that impossible. The contractor has until March 31st to complete the project. We expect the project to be complete by that date.
We are very aware of the inconvenience and disappointment caused by the long closure, and we look forward to being fully open to serve the community at the Federal Way Community Center.
Thank you,
Leif Ellsworth